Review of 2005 |
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| FY2005 | FY2004 | % change | |||
| Sales | (Rm) | 696.1 | 689.2 | 1.0 | |
| Platinum | 401.9 | 425.6 | (5.6) | ||
| Palladium | 74.8 | 92.3 | (19.0) | ||
| Rhodium | 68.6 | 23.6 | 190.7 | ||
| Nickel | 109.3 | 109.4 | (0.1) | ||
| Other | 41.5 | 38.3 | 8.4 | ||
| Cost of sales | (557.3) | (443.3) | (25.7) | ||
| Mining operations | (409.7) | (297.7) | (37.6) | ||
| Concentrating and smelting operations | (104.3) | (114.6) | 9.0 | ||
| Amortisation of mining assets | (53.5) | (46.9) | (14.1) | ||
| Increase in metal inventories | 10.2 | 15.9 | (35.8) | ||
| Gross profit | 138.8 | 245.9 | (43.6) | ||
| Intercompany adjustment* | (27.9) | (13.6) | (105.1) | ||
| Gross profit in Implats group | 110.9 | 232.3 | (52.3) | ||
| * The adjustment relates to sales from Zimplats to the Implats group which at year-end were still in the pipeline. | |||||
| Gross margin | (%) | 19.9 | 35.7 | (44.3) | |
| Other operating expenses | (Rm) | (28.4) | (20.5) | (38.5) | |
| Export incentive | 54.0 | ||||
| Sales volumes in matte | |||||
| Platinum | (000 oz) | 85.8 | 85.2 | 0.7 | |
| Palladium | (000 oz) | 71.5 | 73.2 | (2.3) | |
| Rhodium | (000 oz) | 7.8 | 7.8 | 0.0 | |
| Nickel | (t) | 1,493 | 1,627 | (8.2) | |
| Prices achieved in matte | |||||
| Platinum | ($/oz) | 757 | 724 | 4.6 | |
| Palladium | ($/oz) | 169 | 183 | (7.7) | |
| Rhodium | ($/oz) | 1,424 | 438 | 225.1 | |
| Nickel | ($/t) | 11,828 | 9,738 | 21.5 | |
| Exchange rate achieved | (R/$) | 6.19 | 6.90 | (10.3) | |
| Production | |||||
| Tonnes milled ex-mine | (000 t) | 2,058 | 2,006 | 2.6 | |
| Platinum in matte | (000 oz) | 86.8 | 85.3 | 1.8 | |
| Palladium in matte | (000 oz) | 72.0 | 73.1 | (1.5) | |
| Rhodium in matte | (000 oz) | 8.0 | 7.8 | 2.6 | |
| Nickel in matte | (t) | 1,496 | 1,627 | (8.1) | |
| PGM in matte | (000 oz) | 187.0 | 186.7 | 0.2 | |
| Total cost | 542.4 | 432.8 | (25.3) | ||
| per tonne milled | (R/t) | 264 | 216 | (22.2) | |
| ($/t) | 43 | 31 | (38.7) | ||
| per PGM ounce | (R/oz) | 2,901 | 2,318 | (25.2) | |
| in matte | ($/oz) | 469 | 336 | (39.6) | |
| per platinum ounce | (R/oz) | 6,249 | 5,074 | (23.2) | |
| in matte | ($/oz) | 1,010 | 735 | (37.4) | |
| Capital expenditure | (Rm) | 137.7 | 76.3 | (80.5) | |
| ($m) | 22.3 | 11.1 | (100.9) | ||
Zimplats – platinum production (000 oz)![]() |
Zimplats – cost (R/platinum ounce)![]() |
Zimplats – capital expenditure (R million)
|
|
| Ore reserves | 266.6 million tonnes |
| Mineral resources* | 2,504.8 million tonnes |
| Current production platinum-in-matte | 86,800 ounces |
| Life-of-mine (Phase 1) | 20 years |
| Capital expenditure | $22 million in FY2005 |
| $56 million planned in FY2006 | |
| No. of employees | 1,700, including contractor employees |
| * Inclusive of Ore Reserves. |
At the Selous Metallurgical Complex, both the semi-autogenous mill and the ball mill were relined during the year. Liners of a different design were installed in the semi-autogenous mill in an attempt to improve mill throughput and the efficacy of this is still being assessed. Mill feed was hampered by a one-day national industrial action in November and a breakdown on the primary crusher (a total of 163 hours were lost) at Ngezi. The crusher was taken off-line for repairs at the beginning of July 2005.
Overall concentrator recoveries were hampered by the increase in partially oxidised ore milled in the first half of the year as industrial action by the opencast contractors at the end of the previous financial year disrupted the mining sequence in the opencast mine. Concentrator recoveries improved in the second half of the year with finer grind being achieved and a reduction in the volume of oxidised material processed. Record average recovery levels were reported during the third quarter of the year.
In FY2005, Zimplats shareholders approved a scheme that involved the sale by Implats of its direct 30% stake in Makwiro Platinum Mines (Private) Limited to Zimplats. In return, Implats received 14.9 million newly issued ordinary Zimplats shares which, together with the programme to buy up minority shareholders on the Australian Stock Exchange, brings Implats' holding in Zimplats to 86.9% as at 30 June 2005. This revised structure is aimed at improving the group's ability to borrow funds. Implats strategy remains to buy up the minority shareholders and delist Zimplats from the Australian Stock Exchange. To eliminate confusion regarding the identities of Zimplats and Makwiro, the names of the two companies were changed to Zimplats Holdings Limited and Zimbabwe Platinum Mines (Private) Limited respectively, with effect from 1 July 2005.
In October 2004, the Reserve Bank of Zimbabwe announced that, given the importance of the PGM and platinum mining sector to that country's economic recovery programme, platinum was to be accorded special status, meaning that the metal would fall under the direct control of the Reserve Bank in terms of the 'enhanced platinum sector regime'. This was followed by the promulgation of two statutory announcements which effectively overrode provisions made in the Mining Agreement with the government of Zimbabwe regarding offshore bank accounts. Both Zimplats and its holding company Implats have held extensive discussions with the Reserve Bank of Zimbabwe on finalising a workable arrangement for the management of foreign currency, both for investment funding and for ongoing operational requirements. Additional administrative work is still required and management at Zimplats are currently attending to this and finalising outstanding issues.
Discussions on the empowerment transaction continue with Nkululeko-Rusununguko Mining Company of Zimbabwe Limited. Delays in securing funding for the transaction have in turn led to delays in its conclusion. However, government policy on the indigenisation targets is still to be finalised. Zimplats has been involved in discussions with government and participated in representations from the Zimbabwean Chamber of Mines to government.
Discussions with various government departments continue and clarity is being sought on outstanding issues. Operationally, the plan is to reach full production at the underground mine (Portal 2) at Ngezi and to continue to reduce production at the opencast mine so as to position the company for expansion once the situation in Zimbabwe is clarified.